Burstwick Country Golf & Nineteen Restaurant

View Original

Second studio project now underway

Second Trackman Golf Studio Second Trackman Golf Studio

We are delighted to announce that the build of the second Trackman Golf Studio at the Matt Daley Golf Academy has now commenced with the foundations having been dug out and the timber frame ordered from the supplier.

The builder has told us that the timber frame will be here within the next 10-14 days and then they will be ready to crack on!

The original plan was to mimic the existing studio but after recent discussions this has changed and we have decided to make the second studio bigger, as well as extending the existing studio by 1200mm.

This does make the build quite a bit more complex due to having to strip back the existing roof and create extra structure to change the pitch but we considered that if we were to do this we want it doing to the best specification possible.

We hope to have the room finished within two to three weeks of the builder starting construction of the timber frame, keep an eye out on our social media by clicking below to keep up to date with everything that’s going on.